Ivan Collendavelloo

Ivan Collendavelloo réponds à Bashir Jahangeer au Parlement

Le Premier Ministre par Interim a répondu à deux questions du député de Rivière des Anguilles/Souillac lors de la séance parlementaire du 17 Juillet 2018.

B/634 The Honourable Third Member for Rivière des Anguilles and Souillac (Mr Jahangeer)

To ask the Honourable Deputy Prime Minister, Minister of Energy and Public Utilities:-

Whether, in regard to the laying of water pipes since 2015 to date, he will, for the benefit of the House, obtain from the Central Water Authority, information as to the names of the contractors therefor, indicating the (a) respective contract value thereof and (b) number of litigations, if any, that have arisen in the course of the implementation thereof?

Madam Speaker,

I am informed by the Central Water Authority that since 2015, it has awarded 33 contracts for pipe replacement for the amount of Rs 3.2 billion. I am tabling the list of projects, the contractors and contract value of each project.

With regards to litigations, I am informed that there is litigation in respect of the contract for pipe replacement in John Kennedy Street, Vacoas and the contract for the replacement of mains in Lislet Geoffroy Street, Curepipe.

The dispute has been referred to Dispute Adjudication Board as per the conditions of Contract.

B/636 The Honourable Third Member for Rivière des Anguilles and Souillac (Mr. Jahangeer)

To ask the Honourable Deputy Prime Minister, Minister of Energy and Public Utilities:-

Whether, in regard to the Design, Supply, Installation, Testing and Commissioning of a Combine Cycle Gas Turbine Power Plant at Fort George (CCGT Reference CPB/76/2017), he will, for the benefit of the House, obtain from the Central Electricity Board, information as to where matters stand?

Madam Speaker,
I am informed by the Central Electricity Board that after obtaining the approval of the Central Procurement Board, it launched the bid for the Design, Supply, Installation, Testing and Commissioning of a Combined Cycle Gas Turbine (CCGT) Power Plant at Fort George on 08 February 2018.

At the closing date on 6 June 2018, the Central Procurement Board had received nine bids. The evaluation is presently being carried out.