Le gouvernement réuni lors du Conseil des Ministres a pris note, le 26 juillet 2024, de l’avancement de plusieurs projet routiers sous la responsabilitu de la Road Development Authority dans le pays.
Cabinet has taken note of the status of road capital projects being implemented by the Road Development Authority, including:
(a) the Grade Separated Junction to link the Verdun Bypass and St Pierre Bypass which was completed and opened to the public on 11 July 2024;
(b) the reconstruction of the New Pont Bruniquel at Tombeau Bay which was completed and opened to the public on 23 June 2024;
(c) the upgrading of B28 Road (Lot 3) from Beau Champ to Bel Air which was nearing completion; and
(d) the Stabilisation Works along B103 at Chamarel which was expected to end in January 2025.
(a) the Grade Separated Junction to link the Verdun Bypass and St Pierre Bypass which was completed and opened to the public on 11 July 2024;
(b) the reconstruction of the New Pont Bruniquel at Tombeau Bay which was completed and opened to the public on 23 June 2024;
(c) the upgrading of B28 Road (Lot 3) from Beau Champ to Bel Air which was nearing completion; and
(d) the Stabilisation Works along B103 at Chamarel which was expected to end in January 2025.